RG3 Landfill capping liner protection (Erin LFS)

RG3 Landfill capping liner protection (Erin LFS)

RG3 Landfill capping liner protection (Erin LFS)

Application Function

Filter separators | Protection

Market Sectors

Landfill


In July 2010, as part of its Term Agreement with client Viridor Waste Management, TERRAM RG3 geotextile protection was supplied to Viridor’s Erin landfill site near Chesterfield.

Main contractor Ascot Environmental and sub contractor Masterlay installed the product as a protection to the capping geomembrane for a completed landfill cell.

Project: Erin LFS, Chesterfield
Client: Viridor Waste Management Ltd
Consultant: Scott Wilson Ltd
Contractor: Ascot Environmental Ltd
Masterlay Ltd
Product: TERRAM Robust Geotextile RG3